Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Dragados Offshore, in consortium with Siemens Energy Global, has been selected to develop, build and deliver the HVDC grid stations for the BalWin1 offshore grid connection, alongside BalWin2. Their scope covers the HVDC converter infrastructure, including the offshore converter platform and associated grid station works needed to convert and transmit BalWin1’s 2 GW of offshore wind power to the onshore grid.