Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 15 February 2024, Prysmian Group signed final contracts with Amprion, making it the confirmed cable supplier for the BalWin1 offshore grid connection (as well as BalWin2 and DC34). The package, valued at around €5 billion in aggregate and added to Prysmian’s order backlog, covers approximately 4,400 km of ±525 kV HVDC and dedicated metallic return cables, including the full export cable scope for BalWin1.