Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
On 22 August 2023, Amprion announced that Prysmian Group had been selected as preferred bidder for the HVDC cable systems for the BalWin1 offshore grid connection (along with BalWin2 and the DC34 underground project). Under the preferred bidder agreement, Prysmian committed to reserve the necessary production and installation capacity while the parties negotiate remaining contract details with a target to execute final contracts by 15 January 2024, securing key cable components for BalWin1’s 2 GW ±525 kV HVDC export link.