Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
On 22 May 2024, the Pomeranian Voivode (Wojewoda Pomorski) initiated an administrative proceeding on an application from MFW Bałtyk III Sp. z o.o. for a construction permit covering two subsea export cable sections leading toward transition joint bays (TJBs) and two horizontal directional drillings (HDD) for the Bałtyk III offshore wind farm’s grid connection infrastructure, spanning specified land plots in Lędowo, internal waters and the territorial sea near Ustka.