Onshore construction for the Bałtyk 3 offshore wind farm, developed by Equinor and Polenergia alongside the adjacent Bałtyk 2 project, started in June 2025. The works cover key onshore infrastructure including two substations at Pęplin near Ustka, the onshore export cable corridor to the PSE Słupsk Wierzbięcino grid substation, horizontal directional drilling at the landfall near Ustka, and the operations and maintenance base in Łeba, marking the transition of Bałtyk 3 into the construction phase.