Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
In the first quarter of 2026, the first phase of offshore site preparation for the Bałtyk 2 offshore wind farm (developed together with Bałtyk 3) was completed, consisting of a subsea rock installation campaign that began in January 2026. Using multiple specialised vessels, over one million tonnes of material were placed on the seabed at the Baltic Sea construction site to protect export and inter-array cables and turbine foundations from waves and currents.