Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Sif Holding NV signed final contracts with the Equinor–Polenergia joint venture to supply 100 monopile foundations for the Bałtyk 2 and Bałtyk 3 offshore wind projects in the Polish Exclusive Economic Zone. Manufacturing of the monopiles is scheduled to start in the second quarter of 2025 and finish in the first quarter of 2026, ahead of wind farm commissioning planned for 2027–2028.