Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
ENTSO-E TYNDP 2024 project page for TR 1211 Baltic WindConnector (BWC) shows "Commissioning year estimated by the promoter(s): 2037" (and investment commissioning shown as 12-2037). This is used as the expected full commissioning/commercial service date for the interconnector.