By 15 June 2022, Baltic Power had completed a nine‑month geotechnical survey campaign over its more than 130 km² wind farm site and the over 30 km export cable route, becoming the first wind farm developer in the Polish part of the Baltic Sea to finish such investigations. Using 13 specialised vessels and several hundred personnel, the campaign executed thousands of measurements and deep boreholes at planned foundation locations, providing data to finalise designs for turbine and substation foundations and cable infrastructure and to inform installation technology choices.