Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
By 18 November 2025, ORLEN’s Baltic East offshore wind project had secured a formal decision on preliminary grid connection conditions for the transmission system, confirming reserved grid capacity needed to export power from the planned ~1 GW wind farm. This grid connection decision, held alongside other key permits, allows the project to move forward towards auction participation and subsequent permitting and design work.