install approximately 70 kilometres of 66kV inter-array cables
Van Oord was responsible for the transport and installation of the Baltic Eagle wind turbine foundations and for the supply, transport and installation of the 66 kV inter-array subsea cable system. Van Oord installed the 50 monopiles and continued with transition piece installation, and it installed and buried the inter-array cables using the cable-laying vessel Nexus and the Dig-It trencher.