Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Installation of all 50 Vestas V174‑9.5 MW turbines at the 476 MW Baltic Eagle offshore wind farm was completed in October 2024. According to Iberdrola and Masdar, the turbine installation campaign at the project site ran from May 2024 until its completion in October 2024, enabling subsequent commissioning and energisation activities.