Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By 20 December 2023, termination and testing of the inter-array cables at the Baltic Eagle offshore wind farm were underway, following completion of cable laying by Van Oord’s vessel Nexus and burial using the Dig-It trencher. These commissioning activities on the inter-array system were reported to be in full swing and expected to be completed in the first quarter of 2024.