Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In July 2021, Iberdrola awarded Van Oord a contract to transport and install the 50 monopile foundations and to supply, transport, install and bury the inter-array cables for the Baltic Eagle offshore wind farm, using heavy-lift vessel Svanen, cable-laying vessel Nexus and the Dig-It trencher.