Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Arven targets turbine installation in 2033 as part of the early-2030s offshore construction phase. Per the developer's published timeline, construction is planned over a multi-year campaign ahead of mid-2030s operations; for a 1.8 GW floating wind farm with up to 161 turbines using tow-to-port hook-up onto previously deployed floating substructures, turbine installation typically follows foundation/mooring pre-installation by 12-18 months and precedes first power by 6-12 months, placing turbine installation start in 2033 between 2032 foundation deployment and 2034 first power. Year precision reflects phase-level scheduling on the developer's website.