Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
All 60 Siemens SWT-6.0-154 turbines at the 385MW Arkona offshore wind farm were installed in less than three months, with turbine installation completed by October 2018. This marked the end of the main offshore construction phase for the E.ON–Equinor project in the Baltic Sea and preceded the period in which all turbines were generating power by November 2018.