Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
As part of Arkona’s array cable works, Boskalis carried out offshore site preparation by clearing boulders from the cable routes using its T-Rex boulder clearance tool and then stabilising and protecting the cables with rock berms installed by the dynamically positioned fallpipe vessel Rockpiper.