On 25 April 2016, E.ON awarded Van Oord the contract for the transport and installation of 60 monopile and transition‑piece foundations at the Arkona offshore wind project in the German Baltic Sea, with installation works planned for 2017 using Van Oord’s heavy‑lift vessel Svanen and a feeder concept for floating component delivery.