Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By 24 September 2018, the internal cabling at Arkona had been installed ahead of schedule, with 65 sections of 33 kV array cable totaling about 75 km laid and protected to connect the 60 turbines to the offshore substation, enabling power export during the final construction phase.