Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Sure Partners Limited appointed Arup to support planning and permitting applications for the Arklow Bank Wind Park Phase 2 Onshore Grid Infrastructure, which forms the onshore section of the 220 kV export connection from the offshore wind farm to the National Electricity Transmission Network. The appointment covers preparation of the necessary planning documentation, including route design and environmental assessment for the underground export circuits, substation at Shelton Abbey, and associated overhead line connection.