compose the technical specifications… contracts for procurement and installation of the 33kV submarine cables… FAT of the 45 kilometre 33kV submarine cables
Energy Solutions B.V. supported Parkwind on Arcadis Ost 1’s electrical infrastructure package, including design contribution and verification activities for the wind farm electrical infrastructure. The scope described included calculations and simulations for cable and grid connections, preparation of technical specifications for procurement and installation contracts for the 33 kV submarine cables and the offshore substation electrical system, and quality checks/factory acceptance tests related to the 33 kV array cables.