The first offshore installation campaign at Arcadis Ost 1 was completed in March 2023, with 24 of the 27 turbines installed and most already producing power for the German grid. Parkwind, Heerema Marine Contractors, and Vestas reported that this concluded the initial phase of turbine installation using the floating Rotor Nacelle Assembly (RNA) method, with the remaining three turbines scheduled for installation in autumn 2023.