In 2021, Parkwind awarded JDR Cable Systems a contract to supply, test, and terminate 45 kilometres of 33 kV inter-array cables for Arcadis Ost 1, including sealed cable hang-off systems to connect the project’s 27 Vestas V174-9.5 MW turbines to the offshore substation.