On 28 June 2018, ACER issued a decision on AQUIND Limited’s Article 17 exemption application for the AQUIND Interconnector, deciding not to grant the requested exemption. This ended AQUIND’s initial attempt to obtain a special exemption regime for the project under Regulation (EC) 714/2009, although the company appealed the decision.