On 21 April 2022, Red Eléctrica, together with the Government of Spain, the Regional Government of Andalusia and the Government of Ceuta, formally presented the Peninsula–Ceuta (Andalucia–Ceuta) electricity interconnection as part of Spain’s binding 2021–2026 Electricity Planning, stating that the project foresees an investment of approximately EUR 221 million. The presentations also highlighted expected system-wide economic benefits, estimating annual savings of around EUR 30 million for the national electricity system once the link is in operation, alongside CO2 emissions reductions in the Strait of Gibraltar region.