Vattenfall, RWE, and EWE issued a tender in November 2025 for decommissioning services at the Alpha Ventus offshore wind farm, covering dismantling and transport to shore of all 12 turbine foundations, the offshore substation jacket and topside, and recovery of inter-array cables and related protection systems, with offshore decommissioning works expected to commence from 2027 or 2028, including options for cutting and potentially removing the export cable at the offshore substation.