Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Transmission system operator Terna authorised a 570 MW grid connection for the Agnes Romagna hub off Ravenna, securing capacity on the Italian national transmission network for the Romagna 1 and Romagna 2 offshore wind farms and associated offshore energy facilities, with connection planned at Terna’s La Canala substation.