Per Aarsleff A/S was awarded a contract by HOFOR (Greater Copenhagen Utility) to design, produce, and install 26 gravity-based concrete foundations for the Aflandshage offshore wind farm in the Øresund Strait, including prefabrication at Aarsleff’s Polish factory, transport on barges, and offshore installation scheduled for completion by autumn 2025.