As of 30 September 2025, Terna reported that around 4.8 km of the planned 34 km of civil works for the Adriatic Link’s onshore cable in the Marche region had been completed, production of the second pole of the submarine cable had begun, and supply of key converter equipment for the project’s converter stations was underway.