EDS, part of James Fisher and Sons, was sub-contracted by Boskalis for the cable termination and testing work... EDS completed the cable termination and testing work on the 11 assets... provided HV consulting services... 66kV cabling system.
EDS HV Group (part of James Fisher and Sons) completed work at Vattenfall’s European Offshore Wind Deployment Centre (EOWDC)/Aberdeen offshore wind farm. EDS was subcontracted by Boskalis to perform cable termination and testing across the project’s 11 assets. Separately, EDS HV Management provided HV consulting services to EOWDC, including safety rules implementation, provision of Senior Authorised Persons (SAPs), network and SCADA system review, and commissioning support.