Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
The turbine installation campaign at the European Offshore Wind Deployment Centre (Aberdeen Bay) was completed at the end of May 2018, when the final turbine was installed. The last installation, reported as taking just two hours and 40 minutes and involving a suction bucket jacket foundation, concluded the erection of all 11 turbines at the 93.2 MW offshore wind farm.