GB

The Crown Estate Offshore Wind Leasing Round 4

2021Round 4Pure priceNo revenue mechanism6 winners8.0 GW4 won

Also known as: Offshore Wind Leasing Round 4, The Crown Estate Round 4, Crown Estate Round 4, Round 4, TCE Round 4, UK Offshore Wind Leasing Round 4, England and Wales Offshore Wind Leasing Round 4

Read the full analysis →(17 min read)

Framework Snapshot

First Crown Estate offshore wind leasing round since Round 3 in 2010. At auction open the operative policy backdrop was the March 2019 UK Offshore Wind Sector Deal and its 30 GW by 2030 target. During R4's longer lifecycle UK ambitions rose to 40 GW (2020) and 50 GW (2022), ScotWind concluded in parallel in a different jurisdiction, and downstream CfD allocation rounds remained commercially important companions for project bankability.

Competition
Bidders (preQ → bid → won)

4

Format

Sealed · multi-round

Prize / Award
Award

Agreement for Lease (AfL) + Wind Farm Lease + Transmission Lease

Capacity

8.0 GW

Target delivery

Projects were expected to become operational toward the end of the decade / next decade, following Preferred Bidder Letters in Q1 2021 and AfL signing on 19 January 2023.

Project stage at bidding
pre survey
Commercial terms
Price

GBP 76.2k–154.0k/MW/yr

Payment duration

10 years

Indexation

CPI

Risk allocation
Site investigation
developer
Offshore transmission
developer
Negative prices

Wake-loss support

Curtailment policy

Non-delivery penalties

Missed AfL or Wind Farm Lease milestones can give The Crown Estate termination rights; Wind Farm Lease milestone extensions are permitted for force majeure.

1Prize Composition
Award Components
Agreement for Lease (AfL)(10y)Option for up to 10 years from AfL signing, with exercise required within that period.

Grants exclusivity to develop the seabed site for offshore wind for up to 10 years maximum. During the AfL period the developer undertakes consenting, financing/FID, surveys, and pre-construction work. No planning status is conferred by the auction itself; DCO and marine licensing remain the developer's responsibility.

Wind Farm Lease(60y)Up to 60 years, with a 25-year break clause after construction completion and subsequent rolling 3-year break rights.

Lease for construction and operation of the offshore wind project after AfL option exercise.

Transmission Lease(60y)Similar term structure to the Wind Farm Lease.

Lease for construction and operation of transmission assets associated with the project, on terms similar to the Wind Farm Lease; intended to transfer to an OFTO at divestment.

Site Investigation: developer
State pre-investigated site: No
Transmission Build: developer
Delivery Obligations
Start of constructionSpecific milestone date set in the Wind Farm Lease; supplied extraction confirms the lease contains a start-of-construction deadline but not the numeric date.

The Crown Estate may terminate the Wind Farm Lease if the milestone is missed, subject to permitted force majeure extensions.

Generation dateSpecific generation-date milestone set in the Wind Farm Lease; numeric deadline not stated in the supplied extraction.

The Crown Estate may terminate the Wind Farm Lease if the milestone is missed, subject to permitted force majeure extensions.

Completion of constructionSpecific completion deadline set in the Wind Farm Lease; numeric deadline not stated in the supplied extraction.

The Crown Estate may terminate the Wind Farm Lease if the milestone is missed, subject to permitted force majeure extensions.

TCW: Projects were expected to become operational toward the end of the decade / next decade, following Preferred Bidder Letters in Q1 2021 and AfL signing on 19 January 2023.

Late delivery: Missed AfL or Wind Farm Lease milestones can give The Crown Estate termination rights; Wind Farm Lease milestone extensions are permitted for force majeure.

Extension grounds: Force majeure extensions are permitted for Wind Farm Lease construction milestones.; AfL milestone extensions may be granted on payment of a fee where permitted under the AfL terms.
Prize Consideration (winner → state)
one time upfront

Option Fee Deposit paid on execution of the Preferred Bidder Letter. Formula: one year's Option Fee Bid multiplied by project capacity. On AfL entry, the deposit converts into the first year's option fee payment rather than remaining a separate security.

Trigger: Payable at Preferred Bidder Letter execution at the close of the winning Bidding Cycle.

Anchor: fixed year count

Indexation: none — Single upfront amount based on the winning annual option fee bid; no separate indexation stated for the deposit itself.

The Crown Estate
annual rate per capacity

Annual option fee annuity under the Wind Farm AfL, calculated as the winning bid in GBP/MW/year multiplied by project capacity, CPI-indexed from the signing year.

Trigger: Begins on Wind Farm AfL entry after completion of the Plan-Level HRA and related approvals.

Duration: 10 years

Anchor: until event

Indexation: cpi — CPI-indexed from the AfL signing year.

The Crown Estate
percentage of revenue

Post-exercise Wind Farm Lease rent. During the pre-generation phase, rent is the lower of the annual option fee instalment and the CPI-indexed base rent. During the generation phase, rent is the greater of 2% of gross turnover, a minimum-output limb based on 2% of average project revenue over the previous two years, and the CPI-indexed base rent.

GBP 2 percent of gross turnover

Trigger: Applies under the Wind Farm Lease; generation-phase turnover rent starts when the wind farm begins generating.

Duration: 60 years

Anchor: until event

Indexation: cpi — Base rent and related comparator limbs are CPI-indexed.

The Crown Estate
2Competition Mechanism
Option Fee Bid(GBP/MW/year)↑ Higher wins
Phases: final binding (binding)
Bid Format

Multi-round daily sealed-bid process. In each daily Bidding Cycle, each Eligible Bidder may submit one Eligible Project with an Option Fee Bid in GBP/MW/year. One project is awarded per cycle: the highest-priced bid that passes the cascading eligibility waterfall wins.

sealedmulti-round

Reserve: GBP 250 GBP/MW/yearAll bids must be above the reserve price of GBP 250/MW/year; bids at or below reserve are rejected.

Cycle structure: daily sealed bid (1/day)

Stop: Cycles continue until aggregate awarded capacity is at least 7 GW and projects have been identified across at least three Bidding Areas, subject to a hard maximum of 8.5 GW and a maximum of 3.5 GW in any one Bidding Area. If 7 GW is reached in only two Bidding Areas, at least one further cycle is run in a third area.

Selection: Bids are ranked by descending Option Fee Bid. The highest-priced bid that passes the full eligibility waterfall is selected for that cycle.

Disclosure: After each cycle, The Crown Estate discloses the awarded project's capacity, location, and option fee to Eligible Bidders; bidder identity is withheld until the end of ITT Stage 2.

Selection Envelopes
Minimum aggregate capacity for round closureminimum · awarded_capacity7 GW
Maximum aggregate capacitymaximum · awarded_capacity8.5 GW
Bidding Area capacity capmaximum · awarded_capacity3.5 GW
Minimum Bidding Area diversityminimum · count_of_bidding_areas_with_awarded_projects3 Bidding Areas
3Qualifying Gates
PQQ financial standingformula based

Pass/fail pre-qualification financial standing gate. Extracted thresholds include net assets of at least GBP 70 million, average annual turnover of at least GBP 600 million over the prior three years, and at least GBP 45 million of cash, cash equivalents, or committed undrawn credit facilities from qualifying banks. Consortium members may satisfy these in aggregate in proportion to their proposed project shares.

PQQ technical experienceformula based

Pass/fail pre-qualification technical experience gate. Extracted criteria include project-management experience on commercial projects with at least GBP 25 million expenditure, signed and current HSE policy, regulatory-action disclosure and mitigation, experience entering a grid connection agreement for a project of at least 50 MW since 2009, consent experience since 2009, and EIA management capability including the stated alternative route where only one project type can be evidenced directly.

PQQ legal compliance and bidder structurebinary predicate

Pass/fail pre-qualification legal and bidder-structure gate. Includes mandatory and discretionary exclusion criteria, allowed bidder forms (sole bidder or consortium), prohibition on multiple consortium memberships, identification of the tenant legal entity for the AfL/Transmission AfL, and consortium governance disclosures on reserved matters and deadlock provisions.

ITT Stage 1 development cost plan and capital availabilityformula based18 Six-monthly development cost plan plus rolling 18-month expenditure coverage during a five-year development period

Pass/fail ITT Stage 1 financial robustness gate requiring a high-level six-monthly development cost plan for each project and evidence of sources of funds covering a rolling 18-month look-forward of development expenditure during a five-year development period.

ITT Stage 1 cash availability / Maximum Level of Cash (MLOC) declarationformula based3 Years of development cash requirements including option fee instalments

Bidder must evidence financial capability to cover the first three years of development cash requirements for the proposed project, including option fee instalments. The pre-declared figure then becomes the first cap in the ITT Stage 2 daily-cycle eligibility waterfall.

ITT Stage 1 project definition envelope complianceformula based

Pass/fail project-definition gate covering the extracted project envelope rules: maximum project size 1.5 GW; minimum size 600 MW in Dogger Bank and 400 MW elsewhere; minimum density 3 MW/km²; project wholly within a single Bidding Area; maximum perimeter:sqrt(area) ratio of 5:1; avoidance of hard constraints; minimum 7.5 km spacing from existing offshore wind farms unless owner consent is obtained; no overlap among a bidder's Primary Project Sites; and Variant Project Sites limited to 50-100% of the corresponding Primary Site's area/capacity with at least 50% overlap.

ITT Stage 1 technical criteria and legal agreement acceptancebinary predicate

Pass/fail ITT Stage 1 technical gate requiring identification of development constraints and mitigations, a project schedule aligned to Section 9 milestones, evidence of an appropriate HSE management system and Construction Regulations compliance, acceptance of the forms of legal agreements, and project design information to inform the Plan-Level HRA.

4Scoring Dimensions
Option Fee Bidprice100%higher wins

Method: quantitative formula

Unit: GBP/MW/year

5Tiebreak Chain
  1. total option feeFirst tiebreak: total option fee, calculated as GBP/MW/year multiplied by project MW capacity.
  2. option fee densitySecond tiebreak: option fee density, calculated as total option fee divided by the site area in km².
  3. best and final offerThird tiebreak: Best and Final Offer (BAFO) process with a one-day delay to the subsequent Bidding Cycle; further BAFOs are used as necessary until a unique winner is identified.
6Revenue Mechanism

No revenue-support instrument. Revenue comes from downstream offtake contracts, merchant markets, or bilateral PPAs.

7Authorities & Jurisdiction
The Crown Estatedelivery bodyawarding bodyseabed lessornational

Legal basis: Crown Estate Act 1961 and Energy Act 2004. The Crown Estate ran Round 4, conducted the Plan-Level HRA process for the tender, and entered into the AfLs and leases.

Department for Business, Energy and Industrial Strategy (BEIS)policy ownernational

Legal basis: Contemporaneous UK energy policy department during the R4 tender period; the Secretary of State for BEIS issued the July 2022 no-objection letter on the Plan-Level HRA.

Planning Inspectoratesite planning authoritynational

Legal basis: Planning Act 2008 — post-award development consent order decision-maker for English waters projects.

Marine Management Organisationenvironmental regulatornational

Legal basis: Marine and Coastal Access Act 2009 — post-award marine licensing authority for English waters.

Natural Resources Walesenvironmental regulatorregional

Legal basis: Environment (Wales) Act 2016 and Marine and Coastal Access Act 2009 — post-award marine licensing and consenting authority for Welsh waters.

8Process & Timeline
Process Stages
1. Pre-Qualification Questionnaire (PQQ) — Initial pass/fail pre-qualification stage assessing financial standing, technical experience, and legal compliance.2. Invitation to Tender Stage 1 (ITT Stage 1) — Pass/fail project and bidder robustness stage covering project-definition compliance, technical criteria, development cost planning, and cash-availability declaration.3. Invitation to Tender Stage 2 (daily Bidding Cycles) — Multi-round daily sealed-bid stage in which Eligible Bidders submit one Eligible Project per cycle with an Option Fee Bid in GBP/MW/year.4. Preferred Bidder Letters — Preferred Bidder Letters and Option Fee Deposits are executed at the close of each winning Bidding Cycle; bidder identity is publicly announced only once ITT Stage 2 concludes.5. Plan-Level Habitats Regulations Assessment (HRA) — Post-bidding assessment stage determining whether AfLs can be granted following the Plan-Level HRA and the Secretary of State's no-objection process.6. Agreements for Lease signed — Wind Farm AfLs were signed after satisfactory completion of the HRA process and related approvals.
Timeline Events
1 Sept 2019round launchmonth[The Crown Estate] Round 4 launched in September 2019 with the Information Memorandum and five-stage leasing process.
1 Oct 2019pqq commencedmonth[The Crown Estate] PQQ commenced in October 2019.
itt stage 1 periodrange[The Crown Estate] ITT Stage 1 ran from late 2019 into early 2020.
Invalid Dateitt stage 2 bidding cyclesquarter[The Crown Estate] Winning daily Bidding Cycles occurred in Q1 2021.
Invalid Datepreferred bidder letters signedquarter[The Crown Estate] Preferred Bidder Letters were signed at the close of each winning Bidding Cycle in Q1 2021; this was not a single batch signing on the 8 February 2021 announcement date.
8 Feb 2021tender outcome announced[The Crown Estate] Formal publication of the full Round 4 tender outcome.
plan level hra periodrange[The Crown Estate] Plan-Level HRA screening and appropriate assessment ran across roughly 2020-2022; source documents give differing indicative sub-stage windows, but the process concluded before the July 2022 no-objection letter and January 2023 AfL signing.
1 Jul 2022secretary of state no objection lettermonth[Department for Business, Energy and Industrial Strategy (BEIS)] Secretary of State no-objection letter issued on the Plan-Level HRA.
19 Jan 2023agreement for lease signed[The Crown Estate] Agreements for Lease signed after completion of the HRA process.
9Market Context
Programme
UK Crown Estate offshore wind leasing programme
Policy Targets in Force at Open
UK offshore wind capacity target50 GWby 2030
Regime Events
Jan 2019Offshore Wind Sector Deal 2019policy / sector deal
Narrative ReferenceFirst Crown Estate offshore wind leasing round since Round 3 in 2010. At auction open the operative policy backdrop was the March 2019 UK Offshore Wind Sector Deal and its 30 GW by 2030 target. During R4's longer lifecycle UK ambitions rose to 40 GW (2020) and 50 GW (2022), ScotWind concluded in parallel in a different jurisdiction, and downstream CfD allocation rounds remained commercially important companions for project bankability.
Cross-Axis Structures
Financial Parameter Links
Cash availability / Maximum Level of Cash (MLOC)

Bidder must evidence financial capability to cover the first three years of development cash requirements, including option fee instalments; remaining amount is then tested first in each daily-cycle eligibility waterfall.

Axis 3 gateAxis 2 bid capPre-declared at ITT Stage 1, then reduced by prior provisional awards and reused as the first inter-cycle cap.
Relationships & Sources
Paired Auctions

UK Contracts for Difference (CfD) Allocation Rounds are downstream revenue-support auctions paired with R4. They are commercially essential for most projects' route to market, but not a formal legal prerequisite to hold the R4 lease. As of AR7 results published 14 January 2026, two R4 projects have already secured CfDs.

commercially required
Preceded By1 auction
Followed By1 auction
Source Documents3 documents
Auction Results (6)
WinnerSite/LotCategoryCapacityPriceTotal ValueDeliveryTermMechanismSignedStatus
RWE RenewablesProject identifier 1Bidding Area 11,500 MWGBP 76,203/MW/yr 114,304,500auction clearing
RWE RenewablesProject identifier 2Bidding Area 11,500 MWGBP 88,900/MW/yr 133,350,000auction clearing
Green Investment Group – TotalProject identifier 3Bidding Area 21,500 MWGBP 83,049/MW/yr 124,573,500auction clearing
Consortium of EnBW and BPProject identifier 4Bidding Area 41,500 MWGBP 154,000/MW/yr 231,000,000auction clearing
Offshore Wind Limited, a joint venture between Cobra Instalaciones y Servicios, SA and Flotation Energy plcProject identifier 5Bidding Area 4480 MWGBP 93,233/MW/yr 44,751,840auction clearing
Consortium of EnBW and BPProject identifier 6Bidding Area 41,500 MWGBP 154,000/MW/yr 231,000,000auction clearing