UK CfD Allocation Round 6
Also known as: AR6, UK AR6, CfD AR6, UK CfD AR6, Allocation Round 6, Contracts for Difference Allocation Round 6
Read the full analysis →(67 min read)
AR6 followed the AR5 offshore-wind failure and opened within the continuing UK CfD regime under the Energy Act 2013 / CfD Allocation Regulations 2014, against the 50 GW offshore wind and 5 GW floating-by-2030 policy targets. It drew project pipeline from earlier seabed leasing rounds including Crown Estate Round 3, Crown Estate Round 4, ScotWind and INTOG.
7
Sealed · single-round
Contract for Difference
5.3 GW
Contract-specific Target Commissioning Window of up to 1 year for offshore wind and floating offshore wind per Allocation Framework Schedule 6. The Generator positions the window so the Target Commissioning Date falls within it, no earlier than the first day of the first Delivery Year and no later than the last day of the final Delivery Year, except that later phases of a Phased Offshore Wind CfD Unit may fall beyond the last day of the final Delivery Year.
GBP 54.2–140/MWh (2012 real)
15 years
CPI
For any Settlement Unit in an Intermittent Negative Price Period, the Intermittent Difference Amount is zero.
—
Contractual compensation regime for qualifying curtailment / qualifying partial curtailment under the Standard Terms.
The 15-year clock runs from the earlier of the Start Date and the last day of the Target Commissioning Window, so delayed commissioning erodes the subsidy period day-for-day. If Operational Conditions Precedent remain unsatisfied by the Longstop Date, LCCC may terminate.
15-year two-way Contract for Difference offered to successful applicants; AR6 itself confers no site rights, planning status, or grid-build award.
→ Failure to satisfy the relevant milestone requirements by the Milestone Delivery Date can permit a Pre-Start Date Termination Notice.
→ Failure to deliver the Milestone Requirement Notice, or to satisfy a Milestone Requirement by the Milestone Delivery Date, can permit termination before the Start Date.
→ If relevant OCPs remain unfulfilled at the end of the Target Commissioning Window, the 15-year support term is shortened; if still unfulfilled by the Longstop Date, LCCC may terminate.
TCW: Contract-specific Target Commissioning Window of up to 1 year for offshore wind and floating offshore wind per Allocation Framework Schedule 6. The Generator positions the window so the Target Commissioning Date falls within it, no earlier than the first day of the first Delivery Year and no later than the last day of the final Delivery Year, except that later phases of a Phased Offshore Wind CfD Unit may fall beyond the last day of the final Delivery Year.
Late delivery: The 15-year clock runs from the earlier of the Start Date and the last day of the Target Commissioning Window, so delayed commissioning erodes the subsidy period day-for-day. If Operational Conditions Precedent remain unsatisfied by the Longstop Date, LCCC may terminate.
Stage trigger: An auction is required where valuation shows the applicable budget and/or capacity constraints are exceeded.
Single-round sealed-bid, pay-as-clear allocation. Applicants submit one standard bid plus up to four Flexible Bids per application; qualifying bids are ranked from lowest to highest Strike Price and selected subject to budget, minima and maxima constraints, including Pot 3 sub-caps that produced separate clearing prices.
Reserve: GBP 73 GBP/MWh (2012 prices) — Administrative Strike Price for Offshore Wind in AR6; bids must not exceed the relevant technology- and delivery-year-specific Administrative Strike Price.
Stop: Single sealed-bid submission window followed by one allocation run; selection stops when the next bid or combination would breach the applicable budget, minimum or maximum constraints and no lawful flexible-bid interleaving resolves the breach.
Selection: Walk-the-stack selection from lowest to highest Strike Price, including interleaving of Flexible Bids where permitted.
Applicant must supply the full set of applicable planning consents for the CfD Unit under Regulation 24; this is broader than just DCO or section 36 and includes the relevant development/planning and marine permissions as applicable.
Applicant must supply the required connection agreement(s) under Regulation 25, or a statement that no direct or partial connection applies.
Secretary of State approval of the Supply Chain Plan. Applies to projects at or above 300 MW across the eligible technologies and to all Floating Offshore Wind projects regardless of size. The formal gate is approval statement issued / not issued.
For a Phased Offshore Wind CfD Unit, the completed unit capacity must not exceed 1,500 MW.
For a Phased Offshore Wind CfD Unit, the first phase must represent at least 25% of the total completed unit capacity.
For a Phased Offshore Wind CfD Unit, the first phase must be targeted to complete no later than 31 March of the last applicable Delivery Year.
For a Phased Offshore Wind CfD Unit, the Target Commissioning Date of the final phase must be no later than 2 years after the Target Commissioning Date of the first phase.
Phased Offshore Wind CfD Unit treatment is limited to projects deriving from pre-Round-4 lease arrangements; newer lease cohorts are not eligible for phased-offshore-wind treatment.
No application may be made for a CfD Unit that is or is part of a Generating Station that has already been commissioned.
Method: quantitative formula
Unit: GBP/MWh (2012 prices)
- closest envelope fit — Where tied applications cannot all be accepted without breaching the relevant budget / maximum / minimum constraint, the Delivery Body selects the application or combination that comes closest to filling the relevant envelope without breach.
- electronic random assignment — If multiple alternatives are equally close to filling the relevant envelope without breach, the Delivery Body chooses at random using the electronic random-assignment process.
Legal basis: Operates AR6 within the ongoing Energy Act 2013 and Contracts for Difference (Allocation) Regulations 2014 framework; the Secretary of State issues the relevant statutory notices and Supply Chain Plan approval decisions within that regime.
Legal basis: Delivery Body for AR6 under the Energy Act 2013 / CfD allocation framework; AR6 uses the pre-October-2024 legal name National Grid ESO.
Legal basis: CfD counterparty entering into and administering the awarded Contracts for Difference under the Energy Act 2013 regime.
Legal basis: Statutory 'Authority' determining qualification appeals under the Allocation Framework and Regulations; commonly branded operationally as Ofgem.
Legal basis: Independent auditor appointed under Regulation 36 to audit the allocation process and report to the Secretary of State.
Bid Strike Price must be less than or equal to the relevant technology- and Delivery-Year-specific Administrative Strike Price.
| Winner | Site/Lot | Category | Capacity | Price | Total Value | Delivery | Term | Mechanism | Signed | Status |
|---|---|---|---|---|---|---|---|---|---|---|
| GREEN VOLT OFFSHORE WINDFARM LTD | Green Volt Offshore Windfarm (GV01) | NJ830445 | Pot 2 | Floating Offshore Wind | Delivery Year 2028/29 | 400 MW | GBP 139.93/MWh | — | — | — | auction clearing | — | — |
| INCH CAPE OFFSHORE LIMITED | Inch Cape A | NT394753 | Pot 3 | Offshore Wind Permitted Reduction | Delivery Year 2027/28 | 177.41 MW | GBP 54.23/MWh | — | — | — | auction clearing | — | — |
| INCH CAPE OFFSHORE LIMITED | Inch Cape B | NT394753 | Pot 3 | Offshore Wind Permitted Reduction | Delivery Year 2027/28 | 88.7 MW | GBP 54.23/MWh | — | — | — | auction clearing | — | — |
| MORAY OFFSHORE WINDFARM (WEST) LIMITED | Moray Offshore Windfarm (West) String 9 | NJ432483 | Pot 3 | Offshore Wind Permitted Reduction | Delivery Year 2027/28 | 73.5 MW | GBP 54.23/MWh | — | — | — | auction clearing | — | — |
| EAST ANGLIA THREE LIMITED | EA3B | TM097462 | Pot 3 | Offshore Wind Permitted Reduction | Delivery Year 2027/28 | 158.9 MW | GBP 54.23/MWh | — | — | — | auction clearing | — | — |
| ORSTED HORNSEA PROJECT THREE (UK) LIMITED | Hornsea Project Three Offshore Wind Farm AR6 A | TG210034 | Pot 3 | Offshore Wind Permitted Reduction | Delivery Year 2027/28 | 360 MW | GBP 54.23/MWh | — | — | — | auction clearing | — | — |
| ORSTED HORNSEA PROJECT THREE (UK) LIMITED | Hornsea Project Three Offshore Wind Farm AR6 C | TG210034 | Pot 3 | Offshore Wind Permitted Reduction | Delivery Year 2027/28 | 360 MW | GBP 54.23/MWh | — | — | — | auction clearing | — | — |
| ORSTED HORNSEA PROJECT THREE (UK) LIMITED | Hornsea Project Three Offshore Wind Farm AR6 B | TG210034 | Pot 3 | Offshore Wind Permitted Reduction | Delivery Year 2027/28 | 360 MW | GBP 54.23/MWh | — | — | — | auction clearing | — | — |
| ORSTED HORNSEA PROJECT FOUR LIMITED | Hornsea Project Four Offshore Wind Farm | TA042348 | Pot 3 | Offshore Wind | Delivery Year 2028/29 | 2,400 MW | GBP 58.87/MWh | — | — | — | auction clearing | — | — |
| EAST ANGLIA TWO LIMITED | East Anglia Two, Phase 1 | TM415611 | Pot 3 | Offshore Wind | Delivery Year 2028/29 | 963.07 MW | GBP 58.87/MWh | — | — | — | auction clearing | — | — |