Contracts for Difference Allocation Round 3
Also known as: AR3, UK AR3, CfD Allocation Round 3, Contracts for Difference Allocation Round 3, Allocation Round 3, Third CfD Allocation Round, Third Allocation Round, UK CfD AR3, 2019 CfD Allocation Round, 2019 Contracts for Difference Allocation Round
Read the full analysis →(55 min read)
§2 and §17 of the UK AR3 writeup.
6
Sealed · single-round
Contract for Difference
5.5 GW
1 year for AR3 Pot 2 technologies; the Target Commissioning Window may be extended day-for-day for Force Majeure and specified grid-delay events under the contract definitions.
GBP 39.6–41.6/MWh (2012 real)
15 years
CPI
Difference Amount is zero during rolling negative-price periods: for intermittent technologies, any block of 6 or more consecutive hourly settlement units with negative IMRP; for baseload technologies, 12 consecutive half-hour settlement units where the corresponding 6 hourly IMRP units are negative.
—
Part 11 provides curtailment compensation for Qualifying Curtailment / Qualifying Partial Curtailment, including a four-condition test requiring Change in Law, balancing-mechanism failure limb, causation, and compensation shortfall.
AR3's non-delivery disincentive is contract-termination-without-payment rather than a financial penalty: failure to satisfy the Milestone Requirement or Operational Conditions Precedent can lead to pre-Start-Date termination, and failure to deliver required installed capacity can trigger deemed capacity reduction and termination.
15-year two-way FiT Contract for Difference awarded to successful applicants; LCCC pays the generator when the reference price is below the strike price and the generator pays LCCC when the reference price is above the strike price.
→ By the milestone date the generator must satisfy the Milestone Requirement either through the 10% spend test or by delivering the required Project Commitments and supporting information. Failure allows the CfD Counterparty to terminate before Start Date, subject to the contract response process.
→ If Operational Conditions Precedent are not fulfilled or waived by the Longstop Date, the CfD Counterparty may terminate before Start Date.
→ If the notice is not given on time, Final Installed Capacity is deemed to be 80% of the Installed Capacity Estimate; Final Installed Capacity below Required Installed Capacity is also a termination event.
TCW: 1 year for AR3 Pot 2 technologies; the Target Commissioning Window may be extended day-for-day for Force Majeure and specified grid-delay events under the contract definitions.
Late delivery: AR3's non-delivery disincentive is contract-termination-without-payment rather than a financial penalty: failure to satisfy the Milestone Requirement or Operational Conditions Precedent can lead to pre-Start-Date termination, and failure to deliver required installed capacity can trigger deemed capacity reduction and termination.
Single-round sealed-bid pay-as-clear allocation by Delivery Year. Applicants submit one sealed bid at original application parameters plus up to three additional Flexible Bids, subject to Rule 11 constraints; if no sealed bid is submitted, the Delivery Body assigns a default bid at the applicable Administrative Strike Price.
Reserve: — Administrative Strike Price acts as the hard bid cap / reserve price. For Offshore Wind in AR3, the ASPs were £56/MWh for Delivery Year 2023/24 and £53/MWh for Delivery Year 2024/25.
Application must satisfy Eligible Generator requirements under the CfD regulations; no application may be made for a generating station that has already been commissioned.
Applicant must provide evidence of incorporation, registration, or equivalent legal personality sufficient to enter into the CfD contract.
Applicant must demonstrate that applicable planning consents either do not apply or have been obtained and are sufficient for the proposed CFD Unit's location, capacity, technology, and electricity export arrangements.
Applicant must provide qualifying connection evidence; for direct connection cases the secured capacity must be at least 75% of the Initial Installed Capacity Estimate, with separate agreement evidence per phase where applicable for Phased Offshore Wind.
Any generating station with generation capacity of 300 MW or more must hold a valid Supply Chain Plan Approval Certificate before the main AR3 application window.
Applicant must confirm that the project is not an excluded application by reason of overlapping support such as NFFO, Scottish Renewables Obligation, Renewables Obligation, an existing CfD / Investment Contract, or Capacity Market support, subject to permitted dual-scheme exceptions.
The Target Commissioning Date must fall within the relevant Delivery Year for which the application is made.
Phased Offshore Wind CFD Units must satisfy the structural rules for phased projects: maximum total capacity 1,500 MW, first phase at least 25% of total capacity, first-phase TCD no later than 2025-03-31, final-phase TCD no later than two years after the first phase, and maximum three phases.
Advanced Conversion Technology projects must demonstrate compliance with the Physical Separation Requirement between the synthesis chamber and combustion chamber.
Dedicated biomass with CHP and energy-from-waste with CHP projects must satisfy the June 2018 efficiency standards: at least 70% overall efficiency (net calorific value), 10% primary energy saving (gross calorific value), and 10% heat efficiency (gross calorific value).
Remote Island Wind projects must generate electricity from wind, be located on a qualifying Remote Island, be connected to the national Transmission System or a Distribution System, and satisfy the electrical remoteness test of at least 50 km of cabling of which at least 20 km is subsea.
Method: quantitative formula
Unit: GBP/MWh (2012 prices)
- closest envelope fit — Where tied applications would cause the Monetary Budget or Overall Capacity Cap to be exceeded, select the application or combination of applications that comes closest to fulfilling the Monetary Budget in the final year of the Budget Profile without exceeding the applicable envelope.
- electronic random assignment — If two or more tied applications or combinations are equally close to the Monetary Budget, choose randomly using an electronic random assignment process.
Legal basis: Energy Act 2013 and the Contracts for Difference (Allocation) Regulations 2014 as amended, including SI 2018/1018; BEIS issued the 1 May 2019 AR3 notices and policy documents through the Secretary of State.
Legal basis: Acts as the EMR Delivery Body under the Contracts for Difference (Allocation) Regulations 2014.
Legal basis: CfD counterparty under section 14 of the Energy Act 2013.
Legal basis: Handles Non-Qualification Reviews and Qualification Appeals under the CfD allocation regulations and Allocation Framework section 8.
Legal basis: Appointed under Regulation 36 to audit valuation and allocation calculations for the round.
Legal basis: State aid competent authority for the pre-Brexit EU State Aid regime governing AR3, including scheme approval SA.44475 and Remote Island Wind approval SA.49318.
Offshore Wind ASP = £56/MWh for Delivery Year 2023/24 and £53/MWh for Delivery Year 2024/25, both in 2012 prices.
| Winner | Site/Lot | Category | Capacity | Price | Total Value | Delivery | Term | Mechanism | Signed | Status |
|---|---|---|---|---|---|---|---|---|---|---|
| Doggerbank Offshore Wind Farm Project 1 Projco Limited | Doggerbank Creyke Beck A P1 | Offshore Wind | 1,200 MW | GBP 39.65/MWh | — | 2023 | — | auction clearing | — | — |
| Doggerbank Offshore Wind Farm Project 2 Projco Limited | Doggerbank Creyke Beck B P1 | Offshore Wind | 1,200 MW | GBP 41.611/MWh | — | 2024 | — | auction clearing | — | — |
| Doggerbank Offshore Wind Farm Project 3 Projco Limited | Doggerbank Teeside A P1 | Offshore Wind | 1,200 MW | GBP 41.611/MWh | — | 2024 | — | auction clearing | — | — |
| Forthwind Limited | Forthwind | Offshore Wind | 12 MW | GBP 39.65/MWh | — | 2023 | — | auction clearing | — | — |
| Seagreen Wind Energy Limited | Seagreen Phase 1 | Offshore Wind | 454 MW | GBP 41.611/MWh | — | 2024 | — | auction clearing | — | — |
| Sofia Offshore Wind Farm Limited | Sofia Offshore Wind Farm Phase 1 | Offshore Wind | 1,400 MW | GBP 39.65/MWh | — | 2023 | — | auction clearing | — | — |