Tender for the Thor Offshore Wind Farm

2021Pure pricecfd two way1 winner1.0 GW6 prequalified → 6 bid → 1 won

Also known as: Thor Offshore Wind Farm tender, Thor Offshore Wind Farm, Thor tender, Thor offshore wind tender, Thor offshore wind auction, Thor OWF tender, Danish Thor Offshore Wind Farm tender, Denmark Thor tender, Thor Offshore Wind Farm auction, Thor OWF

Read the full analysis →(24 min read)

Framework Snapshot

Combined Danish offshore wind tender under the Danish Energy Agreement 2018: no separate upstream leasing round, one winner, a two-phase sealed negotiated process, a threshold-gated branched price criterion, and a prize combining site rights, model-licence framework, grid-build responsibility package, and a 20-year two-way CfD.

Competition
Bidders (preQ → bid → won)

6 → 6 → 1

Format

Sealed · 2 rounds

Prize / Award
Award

concession agreement + exclusive site rights + framework of model licences and authorisations + 20-year two-way CfD price premium + grid-build responsibility package

Capacity

1.0 GW

Target delivery

Energinet must have the Point of Connection ready by 2025-01-01; supported operation starts no later than 2027-12-31; at least 95% of licensed capacity must be connected by 2027-12-31.

Project stage at bidding
post survey
Commercial terms
Price

DKK 0.1/MWh

Payment duration

20 years

Indexation

None

Risk allocation
Site investigation
state
Offshore transmission
developer
Negative prices

No price premium is paid for production in hours when the DK1 spot price is non-positive (≤0).

Wake-loss support

Curtailment policy

If DEA appoints Energinet to take over the relevant onshore grid assets, then after construction the TSO must compensate the concessionaire for losses caused by curtailment or other reductions in electricity production in accordance with Section 11.

Non-delivery penalties

Milestone-specific regime rather than a single forfeiture rule: failure to commence construction before 2026-07-01 triggers the defective-performance penalty payable on demand; failure to meet the 95%-connected threshold by 2027-12-31 triggers DKK 280 million per six-month-block completion fines under §3.8-§3.10.

1Prize Composition
Award Components
concession agreementEffective on signature and lapses when the wind farm and internal collection grid have been decommissioned; not a fixed 30-year term.

Concession agreement for the design, construction, operation and decommissioning of the Thor Offshore Wind Farm and its internal collection grid.

exclusive site rights

Exclusive rights over the SEA-narrowed 286 km² Thor site in Danish waters for offshore wind development and exploitation of the wind resource.

framework of model licences and authorisations(30y)The 30-year operational term sits in the operation-phase package, runs from the first commercial kWh delivered and settled to the grid, and may be extended by up to 5 years.

Framework of model licences in Annex 3.1-3.4: preliminary-investigation licence -> licence for construction -> operation-phase licence/authorisation package comprising Annex 3.3 licence to exploit energy and Annex 3.4 authorisation to produce electricity.

20-year two-way CfD price premium(20y)20-year support period.

20-year two-way CfD-style price premium for electricity produced by Thor, settled against a DK1 reference price with bidirectional payment caps.

grid-build responsibility package

Developer responsibility for the offshore wind farm's internal collection grid and the connection up to the Point of Connection, with Energinet responsible from the Point of Connection to the 400-kV grid at Idomlund.

Site Investigation: state
State pre-investigated site: Yes
Transmission Build: developer
Delivery Obligations
Submit project framework and survey planAs soon as possible after conclusion of the concession agreement, and no later than 2022-04-01, the concessionaire must submit the planned project framework, intended preliminary-investigation information, survey plan and related documentation to DEA.

No specific standalone sanction stated in point 2.1; forms part of the post-award licensing sequence.

Submit detailed project time scheduleNo later than 2022-04-01, after signing the grid-connection agreement with Energinet, the concessionaire must submit a detailed time schedule including proposed milestones and proposed subsidy-period commencement.

No specific standalone sanction stated in point 2.4.

Commence construction workConstruction work regarding the offshore wind farm must commence before 2026-07-01.

Failure triggers the defective-performance penalty payable on demand; lapse or termination of the concession agreement requires the separate triggers listed in Section 7.

Connect the offshore wind farm to the collective gridBefore 2027-12-31, the offshore wind farm must be connected to the collective grid. The project is deemed connected when at least 95% of the licensed capacity is connected.

From 2028-01-01, a DKK 280 million completion fine applies for the first six months; an additional DKK 280 million applies every sixth month from 2028-07-01 until the deemed-connected threshold is met.

Provide decommissioning guaranteeAn adequate guarantee for decommissioning the offshore installation must be provided no later than 15 years after supply of the first kWh from the first turbine.

Guarantee must be approved by DEA; no further specific sanction stated in point 6.3.

Submit decommissioning planA dismantling plan must be submitted to DEA no later than two years prior to expiry of the authorisation to produce electricity, or two years prior to decommissioning if earlier.

No specific standalone sanction stated in point 6.3.

TCW: Energinet must have the Point of Connection ready by 2025-01-01; supported operation starts no later than 2027-12-31; at least 95% of licensed capacity must be connected by 2027-12-31.

Late delivery: Milestone-specific regime rather than a single forfeiture rule: failure to commence construction before 2026-07-01 triggers the defective-performance penalty payable on demand; failure to meet the 95%-connected threshold by 2027-12-31 triggers DKK 280 million per six-month-block completion fines under §3.8-§3.10.

Extension grounds: Required licences are delayed for reasons not attributable to the concessionaire, including licences from authorities other than DEA and EPA.; Force-majeure-type events beyond the concessionaire's control, including war, acts of God, fire, strike, lock-out, vandalism, or pandemics.; Grid-connection delays not attributable to the concessionaire, including landowner-agreement failures despite reasonable measures or delay from necessary expropriation.; Weather conditions occurring to a significantly greater extent than usual for the season and area.; Public orders or bans not caused by circumstances attributable to the concessionaire.; Appeals admitted by the relevant appeal boards that delay issuance of the preliminary-investigation or construction licence.; Appeal-board cancellation and remittal of the SEA approval, planning basis, onshore EIA approval, preliminary-investigation licence, or construction licence.; DEA- or EPA-required changes to planning basis, onshore EIA approval, SEA approval, preliminary-investigation licence, or construction licence that cause delay.; Necessary project changes requiring supplementary environmental assessment where the change is necessary because of unforeseen circumstances not attributable to the concessionaire.; Necessary removal of more than four UXOs by Defence Command Denmark.; Defence Command Denmark mitigation measures for radar and radio communication with suspension effect on the project.
Prize Consideration (winner → state)
lump sum within window

Reimbursement of Energinet's preliminary-investigation costs, including onshore EIA work, geotechnical and geophysical surveys, environmental studies, radar-mitigation analysis and MetOcean data.

DKK 151,000,000 DKK

Trigger: Payable after DEA has issued the construction licence; invoiced by Energinet after expiry of the appeal deadline or after final appeal decision.

Indexation: none — Stated as DKK 151 million excluding VAT at current prices, plus interest accrued from 2021-06-01 until payment at the Nationalbank public-company lending rate.

Energinet (100%) — Recovery of preliminary-investigation and related preparatory costs.
lump sum within window

Payment of the actual costs of establishing Energinet's part of the onshore installation, up to the contractual cap stated in point 8.6.

DKK 714,000,000 DKK

Trigger: On the date agreed between Energinet and the concessionaire under annex 3.7.

Indexation: none — Stated as up to DKK 714 million excluding VAT at current prices.

Energinet (100%) — Establishment of Energinet's part of the onshore installation.
lump sum within window

Conditional reimbursement of derived and consequential costs if the concessionaire is responsible for delay or cost increase in Energinet's grid-connection task beyond the capped amount in point 8.6.

Trigger: Triggered if concessionaire-caused delay or cost increase occurs under point 8.7.

Anchor: until condition met

Energinet (100%) — Recovery of derived and consequential costs caused by concessionaire delay.
2Competition Mechanism
Price(DKK øre/kWh)↓ Lower wins

Stage trigger: Branch A applies if the lowest-priced bid's total expected subsidy cost over the 20-year period is below the DKK 3.7 billion (2018 prices) budget evaluation threshold; Branch B applies if no bid is within that threshold.

Phases: probe (non-binding)final binding (binding)
Below-threshold primary branchtriggered

Applies if the lowest-priced bid's total expected subsidy cost over 20 years is below DKK 3.7 billion (2018 prices); award is then automatic without further political approval.

Metric: Lowest bid price per kWh

Branch tiebreak:
  1. highest capacityIf two or more bids have the same lowest bid price in the operative branch, the bid with the highest capacity is preferred.
  2. physical lotteryIf bids remain tied on price and capacity, the winner is chosen by witnessed physical lottery.
Above-threshold fallback branchpolitical approval required

Applies if no bid results in total expected subsidy cost within the DKK 3.7 billion (2018 prices) budget evaluation threshold.

Metric: Lowest total expected subsidy cost over the 20-year period

Branch tiebreak:
  1. highest capacityIf two or more bids have the same lowest total expected subsidy cost, the bid with the highest capacity is preferred.
  2. physical lotteryIf bids remain tied on total expected subsidy cost and capacity, the winner is chosen by witnessed physical lottery.
Bid Format

Two-phase sealed negotiated procedure under sections 61-66 of the Danish Public Procurement Act: prequalified bidders submit an initial non-binding sealed tender, participate in confidential bilateral negotiations, then submit a final binding sealed tender.

sealedmulti-round2 rounds

Reserve: Tender conditions express the admissibility floor as strictly above 0.00 øre/kWh. Because bids are limited to two decimals, the practical minimum bid is 0.01 øre/kWh, but 0.01 is not the stated legal floor.

Selection Envelopes
Installed capacity bandminimum · installed capacity800 MW
Installed capacity bandmaximum · installed capacity1,000 MW
Threshold for branch selectionmaximum · total expected subsidy cost over 20-year period3.7 DKK bn (2018 prices)soft
3Qualifying Gates
prequalificationbinary predicate

Binary pass/fail prequalification stage. Six applicants were prequalified on 2021-01-14 and only prequalified applicants could proceed into the tender process.

technical and financial capacitybinary predicate

Tenderers had to demonstrate sufficient financial and technical capacity, including documented offshore-wind and electricity-generation capability.

state-aid compatibility and beneficiary eligibilitybinary predicate

The round could proceed only once EU state-aid approval was obtained, and the winning bidder had to satisfy state-aid eligibility conditions including not being an undertaking in difficulty and not being subject to an outstanding recovery order for illegal and incompatible aid.

permitted applicant legal formbinary predicate

Single entities, consortia, and not-yet-established subsidiaries or SPVs contingent on winning were permitted applicant forms.

4Scoring Dimensions
Priceprice100%lower wins

Method: quantitative formula

Unit: DKK øre/kWh

5Tiebreak Chain
  1. highest capacityIf bids are tied on the operative primary metric, the bid with the highest capacity is preferred.
  2. physical lotteryIf bids remain tied on the operative metric and on capacity, DEA resolves the tie by witnessed physical lottery. In 2021, several finalists tied at the legal floor and 1,000 MW, so the physical lottery was used.
6Revenue Mechanism
Instrumentcfd two way
Directionbidirectional
Term20 years
Term StartThe 20-year subsidy period begins upon supply of the first commercial kWh from the last wind turbine erected, no later than 2027-12-31, and may commence earlier at the concessionaire's request, but not earlier than first kWh from the first turbine.
Indexationnone — The bid price itself is fixed nominal DKK and un-indexed under §9.3. Separately, the payment caps and the 3 øre/kWh minimum settlement price are adjusted yearly by the net price index.
Reference PriceNord Pool day-ahead hourly spot price in Danish price area DK1.
Price ComputationThe reference price is fixed for each 12-month period and computed as the simple average of hourly DK1 spot prices over the previous calendar year (1 January-31 December), including non-positive-price hours.
Rate Cadenceannual
Payment Cadencemonthly in arrears
Negative Price RuleDeveloper not paid — No price premium is paid for production in hours when the DK1 spot price is non-positive (≤0).
Curtailment CompensationIf DEA appoints Energinet to take over the relevant onshore grid assets, then after construction the TSO must compensate the concessionaire for losses caused by curtailment or other reductions in electricity production in accordance with Section 11.
Payment Caps
state to developer: 6,500,000,000 total net value over 20-year periodnet price index: 2018-price cap adjusted yearly by the net price index.
developer to state: 2,800,000,000 total net value over 20-year periodnet price index: 2018-price cap adjusted yearly by the net price index.
7Authorities & Jurisdiction
Danish Energy Agency (Energistyrelsen)scheme ownerdelivery bodyawarding bodycounterpartynational

Legal basis: Danish Energy Agreement of 29 June 2018; contracting authority under Danish Public Procurement Act sections 61-66.

Energinetgrid system operatornational

Legal basis: Draft concession agreement provisions on Point of Connection readiness, onshore grid works, and compensation.

Kammeradvokatenstate legal advisornational
European Commission DG Competitionstate aid regulatorsupranational

Legal basis: State-aid approval SA.57858 under Article 107(3)(c) TFEU / Article 108(3) notification procedure.

8Process & Timeline
Process Stages
1. Enabling legislation and political authorisation — Thor was authorised politically within the Danish Energy Agreement of 29 June 2018, establishing the programme context and support framework.2. Technical dialogue — DEA conducted preliminary technical dialogue on site investigations and survey scope before launch of the formal tender.3. Market dialogue — DEA held market dialogue on tender conditions and procedures with prospective bidders and investors.4. Prior information notice — Publication of a prior information notice to inform the market about the forthcoming Thor tender and expected prequalification criteria.5. Contract notice and prequalification launch — Formal contract notice and tender materials were published, opening the prequalification process.6. Prequalification — Applicants submitted prequalification materials; only prequalified applicants could continue into the tender procedure.7. Negotiation phase — Prequalified bidders participated in the negotiated procedure, including an initial non-binding tender and confidential bilateral negotiations.8. Final tender conditions published — DEA issued the final tender conditions and updated tender materials for the binding final-tender phase.9. Final tender submission — Prequalified bidders submitted final binding sealed tenders.10. Lottery announcement — DEA announced that the tie at the minimum price and maximum capacity would be resolved by drawing lots.11. Lottery drawn and winner announced — DEA conducted the witnessed physical lottery and announced Thor Wind Farm I/S as winner.12. Concession agreement signed — Completion stage in which the concession agreement is executed after standstill; the exact signing date is not present in the provided extraction.13. Post-award offshore EIA — After award, the concessionaire proceeds through the offshore EIA and the sequential licence and authorisation package under Annex 3.1-3.4.
Timeline Events
29 Jun 2018enabling legislation signed[Parties to the Danish Energy Agreement 2018] Danish Energy Agreement signed, providing the political authorisation for Thor.
13 May 2019technical dialogue[Danish Energy Agency (Energistyrelsen)] DEA held technical dialogue on planned site investigations for Thor.
25 Nov 2019market dialogue[Danish Energy Agency (Energistyrelsen)] DEA held market dialogue on tender conditions and procedures.
31 Mar 2020prior information notice[Danish Energy Agency (Energistyrelsen)] Prior information notice published on TED for the forthcoming Thor tender.
sea public consultation beginsambiguous_range[Danish Energy Agency (Energistyrelsen)] Sources conflict on the start of the public hearing on the Plan for Thor and SEA: one gives 2021-03-01 to 2021-03-29, while another states 2021-02-01 to 2021-03-29.
25 Sept 2020contract notice published[Danish Energy Agency (Energistyrelsen)] Contract notice and tender materials published; formal prequalification launched.
14 Jan 2021prequalification results announced[Danish Energy Agency (Energistyrelsen)] DEA announced that six applicants had been prequalified.
1 Mar 2021state aid approval[European Commission] Commission decision C(2021) 1447 final / SA.57858 adopted.
7 Apr 2021negotiation phase begins[Danish Energy Agency (Energistyrelsen)] Negotiation phase began.
28 Apr 2021negotiation phase ends[Danish Energy Agency (Energistyrelsen)] Negotiation phase ended.
30 May 2021sea approval[Danish Energy Agency (Energistyrelsen)] DEA approved the Plan for Thor and narrowed the site area from 440 km² to 286 km².
24 Jun 2021final tender conditions published[Danish Energy Agency (Energistyrelsen)] DEA published the final tender conditions and updated tender material for the final phase.
8 Nov 2021final bid deadline[Danish Energy Agency (Energistyrelsen)] Final binding tenders were due.
25 Nov 2021lottery announced[Danish Energy Agency (Energistyrelsen)] DEA announced that the tied minimum-price bids would be decided by drawing lots on 2021-12-01.
1 Dec 2021lottery drawn[Danish Energy Agency (Energistyrelsen)] Thor Wind Farm I/S won the concession after a witnessed physical lottery.
concession agreement signed[Danish Energy Agency (Energistyrelsen)] Validation identifies execution of the concession agreement as a canonical stage, but the provided extraction only states that signature was expected within 4-6 weeks after 2021-12-01.
1 Jan 2025energinet poc ready deadline[Energinet] Energinet must have the Point of Connection ready to receive the first kWh by no later than 2025-01-01.
1 Jul 2026construction commencement deadline[Concessionaire] Construction work must commence before 2026-07-01.
31 Dec 2027grid connection deadline[Concessionaire] At least 95% of licensed capacity must be connected by 2027-12-31.
9Market Context
Programme
Danish Energy Agreement 2018
Policy Targets in Force at Open
Denmark 6 GW by 20306 GWby 2030
Zero-subsidy-by-2030 aspirationby 2030
Regime Events
Jun 2018Danish Energy Agreement signedpolicy agreement signed
Mar 2021EU State Aid Decision SA.57858 approvalstate aid approval
Narrative ReferenceCombined Danish offshore wind tender under the Danish Energy Agreement 2018: no separate upstream leasing round, one winner, a two-phase sealed negotiated process, a threshold-gated branched price criterion, and a prize combining site rights, model-licence framework, grid-build responsibility package, and a 20-year two-way CfD.
Relationships & Sources
Source Documents6 documents
Auction Results (1)
WinnerSite/LotCategoryCapacityPriceTotal ValueDeliveryTermMechanismSignedStatus
Thor Wind Farm I/SThor Offshore Wind Farm1,000 MWDKK 0.1/MWhphysical lottery