Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 22 June 2025, the 61st and final inter-array cable was installed at the 488 MW Îles d’Yeu and Noirmoutier offshore wind farm by Louis Dreyfus TravOcean, completing an inter-array connection campaign that began in 2024 and laid nearly 90 km of cables to enable transmission capacity of around 512 MW.