Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
DELAYED +1yr (May 2026): Original 2027 tender date came from the 2024 windopzee.nl routekaart PDF, which the Sept 2025 Actieplan supersedes. The 2026 tender slate is Nederwiek I-A (Oct 2025) plus two 1 GW Routekaart kavels under subsidy; TNW I is NOT in that slate. CfD-based scheme only inzetbaar 'vanaf medio 2027'. Merger investigation with Doordewind unresolved as of 19 March 2026 Doordewind Participatieplan. Earliest defensible permit award is 2028, year precision. --- Dutch government Offshore Wind Energy Roadmap (Windopzee.nl) lists the wind farm zone 'Ten noorden van de Waddeneilanden' (700 MW) with 'Tender: 2027'. Under the Dutch Offshore Wind Act, the tender awards the offshore wind permit (establishment/operation consent) for the site; projecting planning/development consent award in 2027.