Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
DELAYED +3yr (May 2026): Original 2027 estimate came from a 2024-10 Power-Technology / GlobalData profile that pre-dated the Sept 2025 Actieplan + Demo 2 pause. With permit award now projected 2028 and a typical ~2-year permit-to-construction-start window in the Dutch one-stop-shop regime, offshore construction start slips to 2030 (year precision). --- According to a GlobalData/Power Technology profile, construction of the 700 MW Ten noorden van de Waddeneilanden offshore wind project in the Dutch North Sea is likely to commence in 2027, ahead of its planned commercial operation date in the early 2030s.