Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
DELAYED +1yr (May 2026): Original 2033 COD (gem.wiki summary Feb 2026) was a downstream extrapolation of 2027 construction-start. With offshore construction now 2030 and a typical 4-year construction-to-COD window for a 700 MW kavel, COD slips to 2034. Year precision; downstream of the merger-decision outcome and may slip further if TNW I is folded into Doordewind and the 700 MW capacity is delivered earlier via the 4 GW Doordewind site instead. --- The 700 MW Ten noorden van de Waddeneilanden (TNWWFS I) offshore wind farm is now planned to reach full commercial operation in 2033, with Dutch government planning documents and subsequent analyses indicating a two‑year delay from the earlier 2031 commissioning target.