Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Offshore construction for the Saint-Nazaire project commenced in early August 2020 when RTE launched the first installation campaign for the 33 km, 225 kV subsea export cable between La Courance beach and the Banc de Guérande, using the cable‑laying vessel Cable Enterprise to begin marine laying and burial works.