Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Jan De Nul, via its French subsidiary Sodraco International, was awarded a contract to transport and install all 80 GE turbines for the 480 MW Saint-Nazaire offshore wind farm, with turbine installation scheduled to start in early 2022 and be completed by the end of 2022.