Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Louis Dreyfus TravOcean scheduled a second inter-array cable installation campaign at the Saint-Nazaire offshore wind farm to start in mid‑March 2022, deploying the vessel Olympic Triton supported by Wind of Pride and HST Sofia to continue installing the remaining array cables with protective shells and associated seabed stabilisation. This follow-up campaign was planned to complete the full 80-cable inter-array system after an initial 2021 campaign that had installed 20 cables.