Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By mid‑August 2022, Louis Dreyfus TravOcean had completed installation of all 80 inter-array cables at the 480 MW Saint-Nazaire offshore wind farm, finishing a two‑campaign programme in which Prysmian supplied the cables and LDTVO transported, stored and laid them between the turbines using vessels including Olympic Triton and Wind of Pride.