RTE and Ailes Marines (Iberdrola) brought into force their grid connection contract for the Saint-Brieuc offshore wind farm on 6 April 2020, covering a 225 kV double submarine and underground link from the offshore substation to the Doberie onshore substation, enabling RTE to later make the two export connections available for the project.