Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By late 2020, Ailes Marines had selected Van Oord and Saipem to carry out the transport and installation of major components for the Saint-Brieuc offshore wind farm. Van Oord was contracted to transport and install 62 jacket foundations and the offshore substation foundation piles using its installation vessel Aeolus, while Saipem was chosen to install the offshore substation topside, forming the core offshore installation (T&I) package for the project.