Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
A March 2023 project update reports that the inter-turbine (inter-array) cable burial/laying campaign began in January 2023, with Prysmian continuing the work of laying and burying the 90 km of inter-turbine cables (vessels Aethra/Ariadne/Island Diligence). This confirms the start of the Saint‑Brieuc inter-array cable installation campaign in January 2023 (later than the earlier ‘December 2022’ expectation).