Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Prysmian Group, the supplier of the undersea cabling connection systems for Iberdrola’s Saint-Brieuc offshore wind farm in Saint-Brieuc Bay, France, completed its inter-array cable installation scope by December 2023. Iberdrola reports that Prysmian installed and commissioned 90 km of high-voltage 66 kV AC connection cables and three hubs with XLPE insulation for the project. Delivery and commissioning of these cables and associated hubs were completed in December 2023, confirming that the submarine inter-array cable installation campaign for Saint-Brieuc was finished by that time.