Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
On 28 October 2021, the Préfet des Bouches-du-Rhône signed an arrêté préfectoral complémentaire modifying the original arrêté préfectoral d'autorisation environnementale of 18 February 2019 for the Provence Grand Large floating offshore wind farm operated by Parc Éolien Offshore de Provence Grand Large (PEO-PGL). Per the tightened schema, modifications to a project-wide consent (autorisation environnementale by préfet de département) route to consent_variation_awarded. The PGL pilot is a 3-turbine floating wind farm off Port-Saint-Louis-du-Rhône, the first floating wind farm in service in the French Mediterranean.</description> </invoke>