Following the September 2025 AO7 procedure declared infructueuse, Oléron 1 was re-tendered under the merged AO10 / Procédure de Mise en Concurrence n°1/2026 published on 21 April 2026. The AO10 cahier des charges rectificatif vCRE classifies Oléron 1 as Projet 5 of the Groupe PPE3 (fixed-bottom group), with a refined capacity range of 1,150–1,250 MW per §2.9.6 of the cahier. The merged 11-project procedure totals approximately 10 GW (5 GW fixed-bottom + 5 GW floating) across the Normandie, Bretagne, Charente-Maritime, and Golfe du Lion facades, with first lauréats expected to be designated end-2026 / early-2027.