Developer construction-status snapshot — as-built 2026-05-11 Progress: subsea cable >300/725 km laid (all UK waters complete; works continuing in Dutch waters; German nearshore 12 km Hooksiel–Fedderwarden HDD section nearing completion); UK converter station (Isle of Grain, Kent) at full structural height 24 m × 70 m with cladding works underway; DE converter station (Wilhelmshaven) at full structural height 24 m × 70 m with cladding works underway; HVDC transformers 14/14 delivered to site (7 per country, each 7 m × 5 m × >200 t, manufactured at Siemens Energy Nuremberg, barged Rhine→Rotterdam, split 7/7 to Wilhelmshaven and Isle of Grain). This period: Siemens Energy completed delivery of the 7th and final transformer to the Wilhelmshaven converter station site, closing out the full 14-transformer programme; Prysmian crossed the 300 km cumulative subsea-cable threshold with all UK-waters cabling now declared in place; converter station main building structures in both countries reached full 24 m height and entered cladding phase. CEO Arnaud Grévoz quoted: project "remain[s] firmly on track." Active fleet: CLV Leonardo da Vinci (Prysmian) — operating in Dutch waters following completion of UK-waters scope. Source: NeuConnect project news, 11 May 2026.